Proposed Projects

Please check here for the latest information on proposed improvements to our water utility!

  • Upsize water lines on FM 2256 to Inspiration Point Rd
    1st Priority

    Sturdivant Progress WSC has a projected project to upsize the water lines on FM 2256 to Inspiration Rd. To improve water pressure for some of our members.

    Estimated completion costs as of June 2022 is $330,000.00

  • Pressure tanks

    Sturdivant Progress WSC has plans to replace the pressure tanks at the Village Bend pump station.

    Estimated costs as of June 2022 is $25,000.00

    Estimated costs January 2023: $50,000.00

  • New storage tanks and upsize pumps

    Sturdivant Progress WSC has plans to upsize the pumps and install new storage tanks at the Village Bend pump station.

    Estimated costs as of June 2022 is $100,000.00 (NEW estimate October 2022) $200,000.00 Project needs to begin before Fall of 2024

  • Hog Mountain Line and pressure improvements

    Replace aging 8" concrete water supply line on Mog Mnt Rd.

    A 1.5 mile section of 8" concrete pipeline which serves the northeast quadrant of our system is 35 years old and will need to be upgraded. SPWSC has secured easements to lay a second waterline along the old main. Both will be used until the older line is no longer serviceable.

    Estimated costs as of January 2023 - $500,000.00

  • Fence around wells Hwy 281
    March 2023

    Currently taking sealed bids to install fence around wells, to the state specifications

    These wells sold April 2023 - there is no current project to drill more.

    Estimated costs as of January 2023 is $35,000.00

  • Proposed project reserve needed as of January 2023
    $835,000.00